Is completed work running ahead of what you have billed?

Compare earned contract value from cost-to-cost progress with actual billings and receivables.

Example scenario

Editable demonstration inputs, not verified industry benchmarks. Enable JavaScript to calculate your own scenario.

Current contract value
$2,000,000
Estimated total delivery cost
$1,500,000
Delivery cost incurred to date
$750,000
Total billed to date
$800,000
Total cash collected to date
$650,000
Modeled underbilling (negative = overbilling)$200,000

Example result only, not a forecast or promise.

Modeled work earned to date
$1,000,000
Billed receivables not yet collected
$150,000
Cash collected less cost incurred
-$100,000

What to do with this result

Reconcile approved scope and cost-to-complete with the project accountant; this is an operating screen, not a revenue-recognition policy.

Know what is inside the model.

Planning model, not personalized financial advice. Your inputs remain in your browser.

Calculation method

Cost-to-cost completion = incurred costs / estimated total costs. Modeled earned value = contract value × completion. Underbilling = earned value − billed value.

Assumptions and limitations

  • Example inputs are editable scenarios, not Aryo results or independently verified industry benchmarks.
  • Use local quoted costs and your actual job history. Estimates exclude licensing, code, safety and legal determinations.