Is completed work running ahead of what you have billed?
Compare earned contract value from cost-to-cost progress with actual billings and receivables.
Example scenario
Editable demonstration inputs, not verified industry benchmarks. Enable JavaScript to calculate your own scenario.
- Current contract value
- $2,000,000
- Estimated total delivery cost
- $1,500,000
- Delivery cost incurred to date
- $750,000
- Total billed to date
- $800,000
- Total cash collected to date
- $650,000
Modeled underbilling (negative = overbilling)
Example result only, not a forecast or promise.
- Modeled work earned to date
- $1,000,000
- Billed receivables not yet collected
- $150,000
- Cash collected less cost incurred
- -$100,000
What to do with this result
Reconcile approved scope and cost-to-complete with the project accountant; this is an operating screen, not a revenue-recognition policy.
Know what is inside the model.
Planning model, not personalized financial advice. Your inputs remain in your browser.
Calculation method
Cost-to-cost completion = incurred costs / estimated total costs. Modeled earned value = contract value × completion. Underbilling = earned value − billed value.
Assumptions and limitations
- Example inputs are editable scenarios, not Aryo results or independently verified industry benchmarks.
- Use local quoted costs and your actual job history. Estimates exclude licensing, code, safety and legal determinations.