Will this machine upgrade actually increase sellable throughput?

Cap uplift at the slowest downstream step and available demand before valuing an upgrade.

Example scenario

Editable demonstration inputs, not verified industry benchmarks. Enable JavaScript to calculate your own scenario.

Current bottleneck capacity / hour
70
Upgraded capacity / hour
110
Next-slowest process / hour
90
Customer demand / hour
85
Operating hours / year
3,500
Contribution / extra good unit
$12
Upgrade capital cost
$400,000
Annual throughput contribution uplift$630,000

Example result only, not a forecast or promise.

Additional sellable units / year
52,500
Upgrade simple payback
7.6 months
Upgraded constrained throughput / hour
85

What to do with this result

Walk the full process and validate demand; an isolated speed increase may only move the queue.

Know what is inside the model.

Planning model, not personalized financial advice. Your inputs remain in your browser.

Calculation method

Sellable throughput = min(process capacity, next-slowest process, customer demand). Annual contribution = change in sellable throughput × hours × unit contribution.

Assumptions and limitations

  • Example inputs are editable scenarios, not Aryo results or independently verified industry benchmarks.
  • Recovered capacity is not booked revenue or automatic cash savings. Validate the bottleneck, quality and demand before monetizing output.

Turn the number into a decision.

Explore the relevant service

Explore all 200 business decision tools