Contractor Overhead Recovery

The markup every job needs to cover overhead and hit your profit target, and which job types fall short.

Example scenario—not a forecast or verified benchmark. Enable JavaScript to edit inputs, view charts, save locally and export your analysis.

Example inputs

Annual overhead (indirect costs)
450,000
Target net profit (% of revenue)
10
Billable field labor hours per year
24,000
Job mix (next 12 months)
[{"name":"Remodels","directCost":1200000,"markup":30},{"name":"Service & repairs","directCost":400000,"markup":45},{"name":"New construction (sub work)","directCost":600000,"markup":15}]

Example results

Every job needs a 33.8% markup (25.3% margin) to cover $450K of overhead and net 10%; your 28.6% blended markup leaves $114K a year on the table.

Required markup on direct cost
33.8%
Equivalent gross margin
25.3%
Current blended markup
28.6%
Annual shortfall vs. target
$114,444
Break-even markup (zero profit)
20.5%
Projected net profit at current markups
$180,000
Revenue needed
$2,944,444
Overhead per billable field hour
$18.75

What stands out

Blended markup 28.6% vs. 33.8% needed

At current markups you net $180,000 (6.4%) and fall $114,444 short of your 10% profit target.

Markup is not margin: 33.8% markup = 25.3% margin

Markup is a % of cost; margin is a % of the selling price. A contractor who wants a 25% margin but adds 25% to cost comes up $188,218 short on this job mix. To convert: markup = margin / (1 - margin).

New construction (sub work): 15% markup is 18.8 pts short

It does not even cover overhead (break-even markup is 20.5%). Pricing it at the required markup adds $113,030 a year.

Remodels: 30% markup is 3.8 pts short

Pricing it at the required markup adds $46,061 a year.

Each field hour must carry $18.75 of overhead

Add this to loaded labor cost before profit when quoting time-and-materials or service work.

Next actions

  1. Set a minimum markup of 33.8% (a 25.3% gross margin) in your estimating template and require sign-off to go below it.
  2. Re-price new construction (sub work) first: it is the largest gap at $113,030 a year. Raise the markup or stop bidding the lowest-margin work.
  3. Train estimators to quote in margin and show both numbers on every bid so nobody confuses markup with margin.
  4. Re-run this every quarter with actual overhead; recovery breaks when overhead grows faster than volume.

Model assumptions & limitations

  • Required revenue = (direct costs + overhead) / (1 - target net profit %). Required markup = required revenue / direct costs - 1.
  • Assumes overhead is recovered evenly across all direct cost dollars; jobs heavy in pass-through materials or subs may warrant a lower markup and labor-heavy jobs a higher one.
  • Target net profit default (10%) is a common rule of thumb for contractors; set your own.
  • Projected volume and overhead are held constant; raising prices may change win rate.

Explore the relevant Aryo service · All 100 tools