Can your crews deliver the signed workload?

Translate workable days, productive crew hours and job effort into deliverable jobs.

Example scenario

Editable demonstration inputs, not verified industry benchmarks. Enable JavaScript to calculate your own scenario.

Active crews
4
People / crew
4
Scheduled working days / month
22
Hours / person / day
8 hours
Time productive on contracted work
70 %
Productive labor hours / job
160 hours
Jobs promised / month
15
Monthly job capacity above / below promise-2.7

Example result only, not a forecast or promise.

Deliverable job equivalents / month
12.3
Promised job labor hours
2,400
Available productive labor hours
1,971.2

What to do with this result

Check trade dependencies, weather and permits against the schedule; pooled labor hours do not prove the jobs can overlap.

Know what is inside the model.

Planning model, not personalized financial advice. Your inputs remain in your browser.

Calculation method

Job capacity = crews × people × days × hours × productive share / labor hours per job.

Assumptions and limitations

  • Example inputs are editable scenarios, not Aryo results or independently verified industry benchmarks.
  • Use local quoted costs and your actual job history. Estimates exclude licensing, code, safety and legal determinations.